Optimization Design of 600 MW SC Turbine-Generator Foundation

@inproceedings{Yeguang2008OptimizationDO,
  title={Optimization Design of 600 MW SC Turbine-Generator Foundation},
  author={Sun Ye-guang},
  year={2008}
}
Considering actual design conditions of turbine-generator foundation of Huainan Pingwei No.2 Power Plant,optimized foundation design that combines advantages of European and US designs is proposed.It is analyzed theoretically and validated by tests.The designed foundation not only passed 1∶10 model vibration test,but also passed 168 h fully loaded operation test.