Genetic algorithms applied in BOPP film scheduling problems: minimizing total absolute deviation and setup times

@article{Chang2003GeneticAA,
  title={Genetic algorithms applied in BOPP film scheduling problems: minimizing total absolute deviation and setup times},
  author={Pei-Chann Chang and Jih-Chang Hsieh and Yen-Wen Wang},
  journal={Appl. Soft Comput.},
  year={2003},
  volume={3},
  pages={139-148}
}
The frequent changeovers in the production processes indicate the importance of setup time in many real-world manufacturing activities. The traditional approaches in dealing with setup times are that either to omit or to merge into the processing times so as to simplify the problems. These approaches could reduce the complexity of the problem, but often generated unrealistic outcomes because of the assumed conditions. This situation motivated us to consider sequence-dependent setup times in a… CONTINUE READING
Highly Cited
This paper has 19 citations. REVIEW CITATIONS

Citations

Publications citing this paper.
Showing 1-10 of 11 extracted citations

Application of Genetic algorithm on IC substrate drilling path optimization

The 2012 International Conference on Advanced Mechatronic Systems • 2012
View 1 Excerpt

References

Publications referenced by this paper.
Showing 1-10 of 45 references

Multi-objective sequencing with sequence dependent setup times

K. C. Tan, R. Narasimhan
Int. J. Oper. Quant. Manage. 3 • 1997
View 5 Excerpts
Highly Influenced

Scheduling flexible flow shops with sequence-dependent setup effects

IEEE Trans. Robotics and Automation • 2000
View 3 Excerpts
Highly Influenced

Scheduling jobs on parallel machines with sequence-dependent setup times

European Journal of Operational Research • 1997
View 3 Excerpts
Highly Influenced

A branch and bound algorithm for the general job shop with sequence dependent setup times

P. Brucker, O. Thiele
OR Spektrum 18 • 1996
View 2 Excerpts
Highly Influenced

Single machine scheduling using dominance relation to minimize earliness subjective to ready and due times

M. Asano, H. Ohta
Int. J. Prod. Econ. 44 • 1996
View 2 Excerpts
Highly Influenced

Rolling horizon algorithms for a single-machine dynamic scheduling problem with sequence-dependent setup times

I. M. Ovacik, R. Uzsoy
Int. J. Prod. Res. 32 • 1994
View 4 Excerpts
Highly Influenced

A flow-shop problem with sequence-dependent additive setup times

W. Szwarc, J.N.D. Gupta
Naval Res. Logis. Q. 34 • 1987
View 5 Excerpts
Highly Influenced

Approximate schedules for the two-machine flowshop with sequence dependent setup times

J.N.D. Gupta, W. P. Darrow
Indian J. Manage. Syst. 1 (1985) 6–11. 148 P.-C. Chang et al. / Applied Soft Computing 3 • 2003
View 2 Excerpts

Similar Papers

Loading similar papers…