• Computer Science
  • Published 2008

Earned value forecast accuracy and activity criticality

@inproceedings{Vanhoucke2008EarnedVF,
  title={Earned value forecast accuracy and activity criticality},
  author={Mario Vanhoucke and S. Vandevoorde},
  year={2008}
}
This paper presents new simulation results on the forecast accuracy of earned value based metrics to predict a project’s final duration. This is the second paper in a series of papers based on the simulation study initially proposed by Vanhoucke and Vandevoorde (2007b). In a previous manuscript published in the Measurable News (Vanhoucke and Vandevoorde, 2007a), it has been shown that the earned schedule method outperforms, on average, the more traditional earned value based methods to predict… CONTINUE READING

References

Publications referenced by this paper.
SHOWING 1-10 OF 10 REFERENCES

Earned value project management method and extensions

  • IEEE Engineering Management Review
  • 2003
VIEW 7 EXCERPTS
HIGHLY INFLUENTIAL

Forecasting project schedule completion with earned value metrics

D. Jacob
  • The Measurable News,
  • 2003
VIEW 4 EXCERPTS
HIGHLY INFLUENTIAL

Forecasting schedule completion using earned value metrics revisited

D. Jacob, M. Kane
  • The Measurable News,
  • 2004
VIEW 1 EXCERPT

Further developments in earned schedule

K. Henderson
  • The Measurable News,
  • 2004
VIEW 2 EXCERPTS

Schedule is different

W. Lipke
  • The Measurable News
  • 2003
VIEW 2 EXCERPTS

Schedule is different. The Measurable News, Summer:31–34

W. Lipke
  • 2003
VIEW 3 EXCERPTS