Combination of constraint programming and mathematical programming for solving resources-constrained project-scheduling problems

@inproceedings{Jianhai2011CombinationOC,
  title={Combination of constraint programming and mathematical programming for solving resources-constrained project-scheduling problems},
  author={Song Jian-hai},
  year={2011}
}
Combining constraint programming(CP) and mathematical programming(MP) to solve scheduling problems has been an interesting topic for researchers,and promising results are obtained.We propose a preprocessing approach for solving resource-constrained project-scheduling problems(RCPSP) with integer programming(IP) model,and prove an effective inequality theory for the IP model.The effective inequality can be obtained by solving a maximum clique problem which is built on a sub-network of the… CONTINUE READING