A Solution for the Material Delivery Problems in Construction Projects

@inproceedings{AlaRisku2004ASF,
  title={A Solution for the Material Delivery Problems in Construction Projects},
  author={Timo Ala-Risku and Fi},
  year={2004}
}
The new project management methods emerging for construction projects generate new kinds of challenges for the delivery process of the project materials. The basic philosophy of the emerging methods is to create short-term schedules for project tasks based on a constraint analysis of project resources. This approach places two requirements for the material deliveries: Transparency to material availability, and short response times in the supply chain. In this paper, we propose a potential… 

Figures from this paper

An Agent-based Integrated Negotiation Framework of Material Procurement for Lean Construction Material Delivery
TLDR
An agent-based multi-issue automated negotiation framework is given to improve negotiation efficiency and effectiveness and integrates the multi-attribute utility theory and integrative negotiation to suggest better deals with higher joint payoff.
RFID facilitated construction material management - a case study of water supply project
Due to the complex and dynamic nature of the construction industry, construction material management faces many unique challenges from material planning, ordering, receiving and storing, handling and
Tracking based material flow transparency for small and medium sized enterprises
Efficient supply chain management demands transparency for inventory and deliveries along the whole supply network. However, the information technology solutions enabling transparency are expensive

References

SHOWING 1-10 OF 21 REFERENCES
Reforming project management: The role of planning, execution and controlling
In this paper, we focus on the need for reforming the role of plans, execution (or action) and control in project management. We argue that the present style of project management, as described in
THE LAST PLANNER SYSTEM OF PRODUCTION CONTROL
Project controls have traditionally been focused on after-the-fact detection of variances. This thesis proposes a control system, the Last Planner system, that causes the realization of plans, and
Constraint Modeling and Buffer Management With Integrated Production Scheduler
TLDR
A scheduling tool called integrated production scheduler (IPS) is presented to handle the nonprecedence constraints in supply chain and information flow and is feasible to enhance the reliability of look-ahead plans and consequently achieve lean process management.
The four roles of supply chain management in construction
Preconditions and dynamics of logistics networks in the Dutch building industry
Argues that logistics networks in the building industry will develop in relation to transaction‐specific investments in new information technologies such as EDI and PDI. This is particularly the case
Electronic commerce to support construction design and supply‐chain management: a research note
Looks at the changing nature of the construction supply industry and the role of electronic commerce in the evolved market. With the emphasis shifting from supply‐ to demand‐driven product design,
New perspectives on construction supply chain integration
In 1998, a government‐sponsored review of the UK construction sector called for the adoption of initiatives from manufacturing industry in order to increase productivity and reduce costs. Subsequent
Evolution of management theory: the case of production management in construction
In the past 100 years production management has evolved from a set of heuristic ideas to a portfolio of somewhat developed concepts and principles. “Just‐in‐time” and “total quality management”
WORKPLAN: CONSTRAINT-BASED DATABASE FOR WORK PACKAGE SCHEDULING
A database program called WorkPlan has been created to systematically develop weekly work plans. Such work plans are used by crew foremen in scheduling work packages and allocating available labor
...
...